ASSESSING THREATS TO THE ECONOMIC SECURITY OF CONSTRUCTION ENTERPRISES IN UZBEKISTAN BY FREQUENCY AND IMPACT
Keywords:
Keywords: Keywords: economic security; construction enterprise; threat assessment; risk matrix; Likert scale; public procurement; late payment; Uzbekistan.Abstract
Abstract. Construction is one of the fastest-growing sectors of Uzbekistan’s economy, yet its enterprises remain highly exposed to external and internal shocks. This paper identifies and prioritises threats to the economic security of construction enterprises using primary data from a survey of 30 construction firms in Tashkent, Samarkand, Andijan and Khorezm. Respondents rated how often they had faced seven types of threat in 2021–2023 on a five-point Likert scale, and impact was measured through changes in net profit margin, cash-flow disruptions and project delays. The threats were then mapped onto a frequency–impact matrix with explicit classification thresholds. Delayed payments under public contracts (mean score 4.3), construction material price volatility (4.0) and exchange rate fluctuations (3.7) fall within the critical zone, while legal and regulatory uncertainty is a low-frequency, high-impact threat. More than 60% of the surveyed firms use no formal financial or risk planning tools, which amplifies the effect of external shocks. Recommendations are proposed at the enterprise level and for the public procurement system.
References
1.National Statistics Committee of the Republic of Uzbekistan. (2026). Construction statistics. Retrieved October 9, 2026, from https://stat.uz
2.Abulqosimov, H. P. (2006). Iqtisodiy xavfsizlik [Economic security]. Akademiya.
3.Oleinikov, E. A. (Ed.). (1997). Osnovy ekonomicheskoi bezopasnosti (gosudarstvo, region, predpriyatie, lichnost’) [Fundamentals of economic security: State, region, enterprise, individual]. Biznes-shkola “Intel-Sintez”.
4.Zou, P. X. W., Zhang, G., & Wang, J. (2007). Understanding the key risks in construction projects in China. International Journal of Project Management, 25(6), 601–614. https://doi.org/10.1016/j.ijproman.2007.03.001
5.International Organization for Standardization. (2018). Risk management — Guidelines (ISO 31000:2018). ISO.
6.International Electrotechnical Commission. (2019). Risk management — Risk assessment techniques (IEC 31010:2019). IEC.
7.Sambasivan, M., & Soon, Y. W. (2007). Causes and effects of delays in Malaysian construction industry. International Journal of Project Management, 25(5), 517–526. https://doi.org/10.1016/j.ijproman.2006.11.007
8.Akintoye, A. S., & MacLeod, M. J. (1997). Risk analysis and management in construction. International Journal of Project Management, 15(1), 31–38. https://doi.org/10.1016/S0263-7863(96)00035-X
9.Law of the Republic of Uzbekistan No. ZRU-684 “On Public Procurement”. (2021, April 22). National Database of Legislation of the Republic of Uzbekistan. https://lex.uz/docs/-5382974